2002 |
December |
Environmental
Assessment (EA) Process begins for the PEC proposal |
2003 |
January to May |
Community Open
Houses |
2004 |
July |
Conditional Approval to
EA |
| |
November |
Additional public
meetings to review proposal |
2005 |
March |
PEC gets final EA
Approval and permission to proceed with project |
2006 |
August-
November |
Site clearing and preparation |
2007 |
February |
Foundation work
completed for Units 1 and 2 |
| |
June |
Combustion Turbine
Generators for Units 1/2 delivered to site |
| |
July |
Transformers delivered
to site |
| |
September |
Switchyard completed
|
| |
December |
Units 1 and 2 ready for
commissioning |
2008 |
February |
Gas available on
site |
| |
April |
Commissioning completed
for Simple Cycle Operation |
| |
June |
Simple Cycle Operations
in service |
2009 |
February |
Combined Cycle testing
completed |
| |
March |
Combined Cycle
Operations in service |