Timeline

2002

December Environmental Assessment (EA) Process begins for the PEC proposal

2003

January to May Community Open Houses

2004

July Conditional Approval to EA
  November Additional public meetings to review proposal

2005

March PEC gets final EA Approval and permission to proceed with project

2006

August- November Site clearing and preparation

2007

February Foundation work completed for Units 1 and 2
  June Combustion Turbine Generators for Units 1/2 delivered to site
  July Transformers delivered to site
  September Switchyard completed
  December Units 1 and 2 ready for commissioning

2008

February Gas available on site
  April Commissioning completed for Simple Cycle Operation
  June Simple Cycle Operations in service

2009

February Combined Cycle testing completed
  March Combined Cycle Operations in service